 | Y.Bernard replaces J.Bernard. |
 | The maximum weight to transport "easily" is 3.6 tons, which is the limit
of the "tortue" (turtle transport utility,
picture,
picture). An item exceeding this weight is
transportable, but gets more complicated (=time). |
 | The beam attenuator (iron 160x80x80 cm) should be installed in several
pieces with a base of concrete. |
 | The metallic chassis of the nToF cooling unit has to be removed for
transport into TT2A or at least partly modified and reinstalled. |
 | A second floor of concrete will be installed from the step at the
junction of TT2 and TT2A to the first quad in TT2A in order to handle heavy
items more easily. The step has a height of 45 cm. |
 | The double concrete wall on the north side of the TT2 tunnel at junction
is unused. It was installed for a previous design of the nToF line. Its
removal is difficult (as it is a single concrete wall, not individual
blocks). Edges could be modified to allow a larger entrance width. |
 | The weight and the dimensions of the solenoid should be verified:
According
http://198.125.178.188/bnlpulsed/bnl-001R1.pdf the outer dimensions are
length=1.8m, width=?1.3m and height=?1.3m; The weight is about 4 ton. |
 | The base plate of the solenoid should be designed in collaboration with
the transport team to have an usable interface to the transport utilities. |
 | The width of the turtle is 134 cm. Maximum weight for transport is 3.6
tons. |
 | Measured passage at the junction is 135 cm. According to the ACAD
drawing it is 140 cm. |
 | 1 team = 3 persons |
 | estimation de temps pour (1 day = 1 team * 8 hours)
 | opening access pit: 1 day (with 160 tons crane) |
 | closure = opening access pit |
 | installation 2nd floor: 1/2 day |
 | transport solenoid from surface to beam line: 3 day (weight<3.6
tons) |
 | transport solenoid from surface to beam line: 5 day (weight>3.6
tons) |
 | beam dump: 1 day |
 | mercury loop: 1 day |
 | removal of dipoles and quads from/to beam line: 1/2 day |
 | putting down all material from surface down to TT2: 1 day |
 | summary: 8 day, so more or less two weeks |
 | removal is more or less the same depending on the items which are
completely removed or only placed off the beam line.
|
|