2/4/04 TT2A target test CRYOGENICS
present: F.Haug, H.Kirk., B.Pichler, H.Haseroth, A.Fabich
slides presented by F.Haug
-
study made assuming TT2A is the test site.
-
best solution: dewar at top of access shaft of TT2, place concrete fundament,
temporarily a dewar 6000 l. (needs construction permit)
-
Existing dewar (6000 l) in bat. 180 of Atlas and next to building 230, another
50m3 somewhere;
rent a dewar from outside (20kChF/year)
-
200l per cooling cycle (safe estimation), if foreseen for 500 cycles -> 15
refills of large dewar, 10 shots per day -> refill every three days; 1000 l are needed to cool from ambient to operating
temperature.
- why a "permanent"
dewar solution is preferred than mobile dewars
- cold lines (Alcatel Kabelmetall):
simple (for LN2 only) contains
channel for one flow (~500ChF/m); 4x25 meter possible available in bat 180
shielded (for He or LN2 flow)
contains forth- and backflow in one tube (~1000 ChF/m), 2x50 meter possible
available in BA4
- vac pump: approx 1000m3/hour needed
2 primary pumps, ROOT pump 4kW -10
mbar, He 1500 m3/h cooled to 1.9 K, corresponds to LN2 100 g/sec
ROOT pump available (description), small leak -> not useful for He operation, for LN2 is
fine, variable frequency/flow rate adjustment
needs check (outsourced: a few kChF)
and refurbishment (3 man-months)
TT2A LN2 circuit needs to be pumped
to 200 mbar
- passive heater
15-20 kW, He 10-12 g/sec
corresponds to the LN2 100 g/sec needed
size of heater: 1x1.5x2 m3
- to drain LN2 in cold state, a Helium supply is needed to pressurize the
solenoid channels
-
responsibility sharing (doc-version):
FH advises parts designed and constructed in the US.
MIT: designs&constructe DVB (contact
J.Sondericker)
- controls placed towards ISR connected to TT2A via small access gallery,
process control: UNICOS supported at CERN, LabView is not supported
- solenoid
construction: Everson (coils), VCBIT (cryo), Emmaus, Pennsylvania
- time schedule of TT2A
target test, see General&Physics meeting
- to collect the information above
needed 3 man*weeks
- cryogenics estimate: 1.5 man*years, 50 kChF (to be reevaluated in detail)
scheduled videoconference 13.April 17:00-18:00 CERN time (invite as well
B.Pichler, G.Lindell)