31.March 2004, C.Martins, G.Grawer, H.Kirk, A.Fabich
|
item | investment kChF | man-months |
BATTERY solution | ||
purchase batteries | 90 | |
power supply 50 kW | 100 | 3 |
Charge/switch system | 80 ??? (R&D needed) | |
Cabling | 25 | |
Commissioning + safety | 4 | |
TOTAL batteries | 300 | 7 |
RENTAL ALICE TYPE | ||
transport | 3 | |
feasibility + commissioning | 3 | |
rental fee | 0? | |
cables | 75 | |
TOTAL rental | 75 | 6 |
PURCHASE ALICE TYPE | ||
purchase Alice type | 350 | |
installation | 10 | |
Feasibility + contract + commissioning | 9 | |
cabling | 75 | |
TOTAL purchase | 440 | 9 |
money kChF man-months
Battery solution
Purchase batteries 90
Power supply 100 3
Charge/switch system 80 ???(R&D needed)
Cabling 25
Commission/safety 4
===================================================
The list shows only costs, but does not include aspects of reselling and waste
management.
L.Leistam should be urgently contacted to figure out the commissioning schedule
of ALICE.
G.Grawer added to the contact list for power issues.